The development of the Bicycle & Pedestrian Facilities Planning Study began in May of 2009 and will be completed within nine months. Below is a general schedule for the key tasks to be completed in the coming months.
- July 22, 2009: Public Meeting! Click here to learn more.
| Dates |
Tasks |
| June - July 2009 |
Project kick-off, existing conditions analysis, needs assessment, baseline mapping, development and distribution of an online questionnaire, TPB Bicycle & Pedestrian Subcommittee update, and public meeting. |
| July - August 2009 |
Identify station typologies and case studies, field analysis, and best practices research. |
| August - November 2009 |
Develop draft recommendations, cost estimates, and TPB Bicycle & Pedestrian Subcommittee update. |
| November - January 2010 |
Development of final recommendations, implementation strategy and draft plan, and Bicycle & Pedestrian Subcommittee update. |
| January - March 2010 |
Development and review of final plan. |
Public Input
The planning process for the Pedestrian and Bicycle Access Study includes various strategies to gain input from residents, visitors, and key stakeholders. The strategies to gather feedback will include the following:
- Region-Wide Public Workshop to be held July 22, 2009. click here to learn more.
- Online Questionnaire, click here to take the questionnaire (Spanish language version coming soon!).
- Metropolitan Washington Council of Governments Bicycle and Pedestrian Subcommittee Meetings, click here to learn more.